ESOS · Part 6A · Action plans & progress updates · Updated 8 August 2026

ESOS action plan — what to include, deadlines, submission

The action plan you filed in December 2024 is not a closed file. It is the document the Environment Agency will read back to you at the Phase 4 notification, measure by measure, and ask what you actually did.

Three things changed when SI 2026/701 came into force on 22 July 2026 and the Environment Agency published its Phase 4 guidance on 30 July 2026. The nearest one is not in Phase 4 at all — it is 5 December 2026.

Find out which dates are yours Four questions · a dated obligation list · nothing leaves your browser
The action plan cycle2024 → 2031
days until the next action plan deadline — 5 December 2026
5 Dec 2024
Phase 3 action plan
Filed — and still the plan you answer for
5 Dec 2025
Progress update 1
The first of the Phase 3 annual updates
5 Dec 2026
Progress update 2
The nearest live deadline in the whole scheme
5 Dec 2027
Phase 4 notification
Carries the action plan review and achieved savings
5 Dec 2028
Phase 4 action plan
Covering 6 December 2027 to 5 December 2031
5 Dec 2029 · 2030
Progress updates 1 and 2
Published by the Scheme Administrator
5 Dec 2031
Third and final update
New in Phase 4 — most timelines stop at 2030
A plan you filed. A ledger you answer for.
Chapter 01 · The obligation

What is an ESOS action plan?

A statement, signed off by a responsible officer, of the energy-saving measures you intend to take, the savings you expect from each, and when you will deliver them — followed by annual progress updates, in public, for the rest of the phase.

Action plans arrived as Part 6A of the ESOS Regulations, inserted by the ESOS (Amendment) Regulations 2023 (SI 2023/1182).

They turned ESOS compliance from a four-yearly audit into a continuous cycle: after each compliance notification you state what you intend to do with the savings opportunities your energy audit found, and then report progress against those commitments every year, with a responsible officer's name on each submission.

What is new — and what this page is mostly about — is that Phase 4 closes the loop. The plan is no longer only forward-looking. At the Phase 4 notification it becomes evidence, and the regulations now require you to account for it line by line.

Everything above is the plan you filed. Everything below is the ledger you answer for.

Chapter 02 · Key dates

The ESOS action plan deadline — and the seven that follow it

Eight dates run from the Phase 3 action plan in December 2024 to the final Phase 4 progress update in December 2031. Most published timelines stop at 2030.

01
You say what you will do
The action plan: measures, estimated savings, timescales, responsible officer sign-off. Filed after the compliance notification, and published.
02
You report progress every year
Annual progress updates against those same commitments. Also director-signed, also published.
03
At the next phase, you account for it
New in Phase 4. The notification must name every measure you promised and did not deliver, and explain why — regulation 27E.
04
And state what you actually saved
Also new. An estimate of the energy savings achieved across the compliance period, in kWh, per measure — regulation 27D.
5 Dec 2024
Phase 3 action plan deadline
The Part 6A obligation's first deadline. It has passed — but the plan filed against it is the plan the Phase 4 review reads back [1].
5 Dec 2025
Phase 3 progress update 1
The first annual report against those commitments, director-signed and published by the Scheme Administrator [2].
5 Dec 2026
Phase 3 progress update 2 — the next live deadline
The nearest deadline anywhere in ESOS, and it belongs to the action plan, not to the Phase 4 audit. The Environment Agency's own Phase 4 milestone table lists it [6].
31 Dec 2026
Phase 4 qualification date
A snapshot. Whether you are in Phase 4 at all — and so whether the dates below are yours — is decided on this one day [6].
5 Dec 2027
Phase 4 notification — carrying the review
The compliance notification now also carries the action plan review (reg 27E) and the savings actually achieved (reg 27D). This is the date the 2024 plan is marked against [8].
5 Dec 2028
Phase 4 action plan due
A new plan, covering 6 December 2027 to 5 December 2031 — a four-year commitment window [6].
5 Dec 2029 · 5 Dec 2030
Phase 4 progress updates 1 and 2
The familiar annual pattern, against the new plan [6].
5 Dec 2031
Phase 4 progress update 3 — final
New. Regulation 28 of SI 2026/701 added a third update for compliance periods ending on or after 5 December 2027, due between the three- and four-year anniversaries of the start of the relevant compliance period [7].

The full ESOS deadline tracker carries the audit and qualification dates alongside these; this page carries the action plan cycle.

Chapter 03 · The live one

5 December 2026: the deadline almost nobody is counting down to

Every competing guide treats the action plan as a 2024 event. The Environment Agency's own Phase 4 milestone table opens with a Phase 3 obligation that is still running.

days to Phase 3 progress update 2
What the update has to say

Progress against each measure in your Phase 3 action plan, for the year to 5 December 2026 — implementation status, the savings actually achieved against the savings you estimated, the reason for any variance, revised timescales, and any measure you have added since [1][2].

Who signs it

A responsible officer — a director within section 250 of the Companies Act 2006, or a person exercising management control (regulation 30(2)). The same sign-off standard as the assessment and the plan itself [6].

Where it goes

Through the MESOS service, and it is then published by the Scheme Administrator [3][6].

If your Phase 3 notification was never filed, MESOS will not accept the update: the compliance notification has to be in first. That sequencing trap is the single most common reason an update is late.

Chapter 04 · Your dates

Which of these dates are actually yours?

Four questions. The answer is a dated list of the action plan obligations that apply to your organisation, with the regulation behind each one.

This tool computes from what you enter and nothing else. It does not decide whether you qualify for Phase 4 — the qualification test itself lives on the ESOS Phase 4 compliance guide, which owns that question. Nothing you type leaves your browser.

Chapter 05 · 22 July 2026

What SI 2026/701 changed about action plans

Three amendments, all in force since 22 July 2026, and all of them about the plan you have already filed rather than the one you have yet to write.

Reg 17
A new Chapter 3B, and regulations 27D and 27E
Titled “Energy savings since the previous compliance period and ESOS action plan review”. It puts both new duties inside the ESOS report and the notification of compliance [8].
Reg 27D
Report the savings you actually achieved, in kWh
An estimate of energy savings achieved in the compliance period, the measures that produced them, each measure's energy-saving category, and each measure's saving in kWh [8].
Reg 27E
Review the plan — and name what you did not do
Identify every measure in your current action plan not implemented and not expected to be implemented before the end of the compliance period, and explain why [8].
Reg 28
A third progress update, and kWh as the unit
Adds a final update for compliance periods ending on or after 5 December 2027, and changes reg 34B(3)(b) from “energy measurement units” to kWh [7].

The direction of travel is one thing: the action plan is being made auditable. Each amendment converts something that used to be narrative into something with a unit, a category, or a required explanation. The full instrument is on legislation.gov.uk, and ESOS legislation sets out how the 2014, 2023 and 2026 instruments fit together.

Chapter 06 · Regulation 27E

The action plan review — the part no competing guide names

Regulation 27E is four lines long and it changes what an action plan is for.

Regulation 27E(2), inserted by SI 2026/701 reg 17
“…identification of any measures recorded in any current ESOS action plan which have not been implemented, and are not expected to be implemented, before the end of the compliance period… and an explanation of the reasons why those measures were not implemented.”

Read the phrase “and are not expected to be” carefully. The review is not a retrospective tally of what slipped. It asks you to make a forward judgement, in a statutory submission, about measures you have not yet abandoned.

A measure still notionally on the capital plan for 2027, which you privately know will not land, has to be declared as not expected to be implemented — with a reason.

Three consequences follow, and none of them are on the first page of Google.

One
It lives in the notification, not in the plan
The review is part of the ESOS report and the notification of compliance — the 5 December 2027 submission, not the 2028 action plan [8].
Two
It is per-measure, not a summary
Appendix B records it as two separate notification fields: the measures, and then for each, an explanation [10].
Three
It is not published — with one exception
The measures and reasons are notified but not published. The exception is in the next chapter but one, and it is the one that matters [10].

The practical implication is about people, not paperwork. The reasons a 2024 measure was not implemented are known in 2026 by the engineer, the finance lead or the site manager who made the call. By December 2027 some of them will have left. Recording the reason now, against the measure, is the whole job.

Chapter 07 · Draft it

Compose your regulation 27E review

Enter the measures from your current action plan and mark what happened to each. This produces the two statutory blocks your Phase 4 notification has to carry — the 27E review and the 27D achieved-savings statement — and flags anything the regulations would treat as incomplete.

Working text, not a submission. The wording of your notification is yours and your lead assessor's responsibility, and a false or misleading statement in a notification is an offence under regulation 47 — up to £50,000 and publication [6]. Nothing you type leaves your browser.

Chapter 08 · Regulation 27D

The savings you actually achieved, in kWh

The companion duty to the review, and the one that changes what your monitoring has to be able to produce.

Regulation 27D requires an estimate of the energy savings your organisation achieved during the compliance period — for Phase 4, the whole span from 6 December 2023 to 5 December 2027 — expressed in kWh [8].

It is not a single number. The notification carries four separate things: the total, a breakdown by organisational purpose, the measures that produced the savings, and for each measure its energy-saving category and its own kWh figure [10].

Total estimated savings achieved — reg 27D(1)Published
The combined figure across all measures is the only savings number the Scheme Administrator publishes [10].

The unit matters more than it looks. Until 22 July 2026 the equivalent progress-update field read “energy measurement units”; regulation 28 changed it to kWh [7]. An organisation whose measures are tracked in litres of diesel, therms, or tonnes of steam now has to convert, consistently, and keep the conversion basis — because the same measure will be reported again in 2029, 2030 and 2031.

If your energy audit estimated a measure's saving one way and your monitoring reports it another, the variance shows up in the progress update, not in an internal review.

Chapter 09 · Publication

What the Scheme Administrator actually publishes

Appendix B of the Phase 4 guidance carries a column headed “Published by the scheme administrator?” against every field in the notification. It is the most precise answer available to the question everyone asks, and it is not on any competing page.

Every row is quoted from Appendix B: Information to provide through the ESOS notification system (ODT, 30 July 2026), Table B10, with the regulation reference the Appendix gives [10]. Appendix B is guidance; where it and the ESOS Regulations 2014 as amended conflict, the regulations take precedence — the Appendix says so itself [4][10].

Chapter 10 · Consequences

There is no fine for missing an action plan — and that is not the end of it

Two things are true at once, and most guidance carries only the first.

The Environment Agency's Phase 4 guidance states that regulators “will not take enforcement action or issue a penalty relating to the non-submission of an action plan or progress update” [6]. There is no civil penalty attached to the action plan duty. Any guide telling you a missed action plan carries a fine is describing a regime that does not exist.

The second thing is what replaces it, and it is in Appendix B rather than in the guidance body, which is probably why nobody has written it down.

Regulation 27E(2)(c) — the published admission

Where you were required to produce an ESOS action plan and did not, your Phase 4 notification must carry “confirmation that the participant was required to produce an ESOS action plan but did not do so”.

Appendix B Table B10 marks that field, alone in its block, as published by the Scheme Administrator — while the measures and the reasons around it are not [10].

So the sanction is not a penalty. It is a declaration you have to make about yourself, three years later, in a director-signed statutory submission, which is then published on the register alongside your name.

And a false or misleading statement in that notification is an offence — regulation 47, up to £50,000 plus publication [6]. The route from “no penalty for the action plan” to a penalty runs through mis-stating the review, not through missing the plan.

The penalties that do attach to ESOS attach elsewhere: failure to notify (reg 43, up to £5,000 plus £500 a working day capped at 80 days), failure to keep records (reg 44), failure to undertake an audit (reg 45, up to £50,000), and failure to comply with a notice (reg 46) [6]. ESOS penalties sets out the whole schedule.

Chapter 11 · Contents

What an ESOS action plan must include

Four required fields and two that separate a plan which survives three public progress updates from one that does not.

Required
A statement of intent
Whether the organisation intends to reduce its energy consumption over the phase. A plan may say it will take no measures — but that statement is published [1][6].
Required
The energy-saving measures
The specific measures you intend to implement, drawn from — or going beyond — the opportunities the assessment identified [1].
Required
Estimated energy and cost savings
Per measure. Record the estimation method with it: reg 27D will ask for the achieved figure in kWh against this baseline [1][8].
Required
Implementation timescales
When each measure lands, within the phase. Unmet timescales are what reg 27E asks you to explain, so optimism here is expensive later [1][8].
Good practice
A breakdown by organisational purpose
Buildings, transport, industrial processes, other. Reg 27D(2)(a) requires exactly this split for achieved savings — so a plan built the same way reconciles without rework [8][10].
Good practice
Energy-saving category per measure
Not a statutory field in the plan — but reg 27D(2)(c)(i) requires the category of each implemented measure. Tagging at plan stage removes a reconciliation in 2027 [8].

The two good-practice rows are the practical advice this page can give that the regulations do not: build the plan in the shape the review will ask for. Reg 27D and reg 27E did not exist when Phase 3 plans were written, which is precisely why reconciling a 2024 plan against them in 2027 is work.

Keep the content suitable for disclosure. Plans and updates are published; commercially sensitive operational detail can be summarised at measure level without losing the substance.

Chapter 12 · Templates

Is there an official ESOS action plan template?

No — and the honest version of that answer is more useful than the answer itself, because GOV.UK does publish two templates and neither is the one people are looking for.

The Environment Agency's Phase 4 publication page carries exactly six documents [5]. We checked it directly on 8 August 2026. None of them is an action plan template.

HTML
How to comply with ESOS phase 4
The guidance body. Section 10 covers the ESOS report; the milestone table carries every date [6].
HTML
Appendices A1 and A2: Report checklists for participants
Checklists for the ESOS report, not the action plan [12].
ODT
Appendix A3: Example template of phase 4 ESOS recommendations
A recommendations template — the output of the audit, which is what a plan is built from. This is the document most often mistaken for an action plan template [11].
ODT
Appendix B: Information to provide through the ESOS notification system
Twelve tables of every notification field, with a publication column against each. The closest thing to a field list that exists [10].
HTML
Appendix C: Advice for complying with ESOS
General compliance advice [13].
HTML
Appendix D: Useful contacts and information
Regulator contacts by nation [14].

So the practical answer has two halves. The plan itself is entered into the MESOS form against the categories the regulations set — there is no document to download and fill in. The content can be prepared in advance, and that is what a template is actually for.

Preparing the content field by field

Our ESOS templates page lays the same structure out as a field-by-field table, alongside equivalent structures for the energy audit evidence pack and the assessment record. It is the page on this site that owns ESOS template intent, and it is the better starting point if a document to work from is what you want.

Chapter 13 · Filing

ESOS action plan submission — the MESOS sequence

Online only, through one Environment Agency service, in an order that cannot be varied.

01
The compliance notification goes first
MESOS will not open the action plan or progress update forms until the phase notification for that participant is filed. Late compliers must clear the notification before anything else [3][6].
02
Prepare the content offline
Measures, estimated savings, timescales, and — from Phase 4 — the category each measure falls into. The form is not a good drafting environment.
03
A responsible officer signs off
The assessment, the action plan and every progress update each require director sign-off before submission [6].
04
Submit through MESOS
The same portal as the notification of compliance and the compliance report [3].
05
Then the annual updates, on the same route
Each December, against the same plan, until the phase closes.

One consequence of step 1 is worth stating plainly: an organisation that never filed its Phase 3 notification has not simply missed one deadline. It cannot file the action plan, and it cannot file either progress update, because the service will not let it — and the notification failure is the one that carries a civil penalty [6].

Chapter 14 · Sources

Where the ESOS action plan guidance actually lives

Four documents, in the order you would read them, and what each one is good for.

Start
How to comply with ESOS phase 4
The Environment Agency's guidance body, published 30 July 2026. The milestone table, sign-off rules and the penalty schedule at § 15.1 [6].
Fields
Appendix B
Every notification field, its regulation, whether it is new, and whether it is published. Table B10 is the action plan block [10].
Law
SI 2026/701, regulations 17 and 28
The binding text for the review, achieved savings and the third progress update. Read these when the guidance is ambiguous [7][8].
Origin
SI 2023/1182, Part 6A
Where the action plan duty came from, and still the source for what a plan must contain [1].

The GOV.UK ESOS scheme hub sits above all four and is the right first stop for anything outside the action plan cycle [2].

One caution about older material. A large amount of published commentary predates 30 July 2026 and says Phase 4 guidance was expected in early 2027. It was published on 30 July 2026, and the position on DECs, Green Deal Assessments, ISO 50001 coverage and the number of progress updates all changed with it. Check the date on anything you read, including ours — this page was last verified on 8 August 2026.

Chapter 15 · Progress updates

ESOS progress updates and progress reports

Phase 3 carries two. Phase 4 carries three. They are the same instrument, filed annually, and they are the part of the cycle most often missed.

A progress update reports implementation against the action plan for the year: what was installed, what it saved against what you estimated, why anything varied, revised timescales, and any measure added since the plan was filed [1][2].

“Progress report” is not a term the regulations use. The statutory instrument is a progress update under regulation 34B, and searching for one will find the other.

Phase 3 — two updates
  • 5 December 2025 — update 1, passed
  • 5 December 2026 — update 2, next due
Against the plan filed by 5 December 2024 [1][6].
Phase 4 — three updates
  • 5 December 2029 — update 1
  • 5 December 2030 — update 2
  • 5 December 2031 — update 3, final — new [7]
Against the plan due 5 December 2028, covering 6 December 2027 to 5 December 2031 [6].

The third Phase 4 update comes from regulation 28 of SI 2026/701, which inserts a requirement for a final update “during the period starting on the three year anniversary of the first day of the relevant compliance period and ending on the day before the four year anniversary”, for compliance periods ending on or after 5 December 2027 [7].

Regulation 28 also exempts participants relying on regulation 33A — the zero-consumption route — from the progress update duty [7].

One question we are not answering yet

Regulation 34B(8) defines “relevant compliance period” by reference to regulation 34A(10), which reads it as the compliance period following the one the notification relates to. Applied literally to Phase 3 action plans, that definition appears to bring them within regulation 28's condition as well, which would imply a third Phase 3 progress update.

The Environment Agency's own Phase 4 milestone table does not list one, and no competing source raises it. Until the Environment Agency confirms that reading we are not publishing a date against it. Plan for two Phase 3 updates, as the milestone table says — and treat this note as the reason to check back rather than as a deadline [6][7].

Chapter 16 · The next cycle

The ESOS Phase 4 action plan — what comes next

A new plan follows the Phase 4 notification, and it commits you for four years rather than three.

The Phase 4 action plan is due 5 December 2028 and covers 6 December 2027 to 5 December 2031 [6]. That window is the reason there are three progress updates rather than two: a longer commitment period gets an extra checkpoint.

Writing it is a different job now that reg 27D and reg 27E exist. A Phase 4 plan will be read back in the Phase 5 notification the same way the Phase 3 plan is being read back now — so the estimation method, the category tagging and the organisational-purpose split are worth settling once, at plan stage.

Qualification, the audit, and the 5 December 2027 notification

Whether Phase 4 applies to you at all is decided by the 31 December 2026 qualification snapshot, and the audit that has to sit behind the notification is a separate body of work. Both belong to the ESOS Phase 4 compliance guide, which owns ESOS Phase 4 on this site — including the Phase 4 checklist and the qualification test. This page picks the story up at the plan.

Chapter 17 · Phase 3

Phase 3 is history — except for the parts that are not

The Phase 3 action plan deadline passed on 5 December 2024. Two obligations arising from it are still live, and one of them is the next date in the scheme.

The headline ESOS action plan deadline for the Phase 3 cycle was 5 December 2024. The Environment Agency operated an extended acceptance window after it, during which late submissions were accepted without remedial action.

We have not been able to locate a primary Environment Agency publication stating the closing date of that window, although a specific date circulates widely in secondary sources. Rather than restate an unsourced date, the accurate position is this: the extended window is closed, and a Phase 3 participant that has still not filed should file now — there is no penalty for the late action plan itself, and filing removes the reg 27E(2)(c) declaration from your Phase 4 notification [6][10].

That last point is the practical reason to act on a two-year-old deadline. Filing the plan late is not penalised. Not filing it at all becomes a published statement about your organisation in December 2027.

Still live
Progress update 2 — 5 December 2026
Against your Phase 3 plan. Listed in the Environment Agency's Phase 4 milestone table because it runs into the Phase 4 period [6].
Still live
The plan itself, as evidence
Your Phase 3 plan is the “current ESOS action plan” that reg 27E reviews at the Phase 4 notification [8].
Chapter 18 · Reuse

The same data, in your climate disclosures

An action plan is quantified, signed off by a responsible officer, dated and externally published. Very little else an organisation produces is all four.

For organisations that also report climate disclosures, the action plan cycle is an asset rather than a duplicate burden. The measures, their estimated savings and their delivery timescales are the same underlying data that UK SRS transition planning disclosures ask for, and the achieved-savings figures reg 27D now requires are exactly the kind of implementation evidence a transition plan is judged on.

The same figures support the energy-efficiency narrative in SECR energy and carbon reporting, and the metrics-and- targets pillar under UK SRS S2.

The regimes stay distinct — SI 2026/701 did not align the ESOS and SECR thresholds, and that alignment remains deferred [9]. But ESOS and UK SRS integration sets out where the same data can legitimately serve both, which is most of it.

Chapter 19 · Support

Doing it in-house, or not

Most action plans are written in-house from the assessment. Two situations reliably justify outside help.

The plan itself is not technically hard: the measures come from the ESOS assessment, and the estimates come from the audit. Most organisations draft it internally and have their lead assessor review it.

Case 1
Implemented measures went beyond the recommendations
Reg 27D wants achieved savings per measure in kWh. Quantifying a measure the audit never modelled needs someone who can defend the method [8].
Case 2
The people who made the 2024 decisions have gone
Reconstructing why a measure was dropped, three years on, is the reg 27E problem — and it is an evidence problem, not an energy one [8].

ESOS consultants and assessors covers how the market is structured and what to ask for. ESOS requirements sets out the wider duty set if you are checking scope before deciding.

Nineteen chapters, and it still comes down to one filed document and eight Decembers.

Retrieve the action plan you filed in December 2024, mark every measure as delivered or not, and write down the reason next to each one now — because in December 2027 the Environment Agency will ask you for exactly that list, and the only part of it made public is the admission that you never filed a plan at all.

5 December 2026 is the next deadline in ESOS
Phase 3 progress update 2. Not a Phase 4 date, and nearer than any of them.
Regulation 27E reviews the plan you already filed
Every measure not implemented, and not expected to be, with a reason for each — inside the 5 December 2027 notification.
Achieved savings are reported in kWh, per measure
Regulation 27D. Only the combined total is published; the per-measure figures are notified but withheld.
There is no fine for a missed action plan
The Environment Agency says so directly. Penalties attach to notification, records, the audit and false statements — not to the plan.
But not filing one becomes a published admission
Regulation 27E(2)(c): confirmation that you were required to produce a plan and did not. Appendix B marks that field as published.
Phase 4 carries three progress updates
5 December 2029, 2030 and 2031. The third one is new, and most published timelines stop before it.
There is no downloadable action plan template
GOV.UK publishes six Phase 4 documents. Appendix A3 is a recommendations template; Appendix B is a notification field list. Neither is a plan.
MESOS will not take a plan before the notification
The compliance notification unlocks the action plan and progress update forms. Clear it first.

The plan is only half the duty. The other half is the notification it gets read back inside — and that one carries a penalty.

See what the 2027 notification asks for Or put every ESOS date in one tracker
The dates behind this page
6 Dec 2023Phase 4 compliance period opens
5 Dec 2024Phase 3 action plan deadline
22 Jul 2026SI 2026/701 in force
30 Jul 2026EA Phase 4 guidance published
5 Dec 2026Phase 3 progress update 2
5 Dec 2027Phase 4 notification — the review
5 Dec 2028Phase 4 action plan due
5 Dec 2031Third and final progress update
days to the next action plan deadline — 5 December 2026
Answer the four questions in “Which of these dates are actually yours?” and your next date appears here.
The sourced record
ESOS action plan requirements

Requirements — the full reference

Every action plan duty across the cycle, consolidated, with the provision behind each.

Duty 1
Produce an action plan after each compliance notification
Part 6A of the ESOS Regulations 2014, inserted by SI 2023/1182. Phase 3: due 5 Dec 2024. Phase 4: due 5 Dec 2028 [1][6].
Duty 2
State intent, measures, estimated savings and timescales
The four required content fields, entered against the categories the regulations set [1].
Duty 3
Obtain responsible officer sign-off
On the assessment, the action plan and every progress update, before submission [6].
Duty 4
Submit through MESOS, after the notification
The action plan and progress update forms unlock only once the phase notification is filed [3][6].
Duty 5
File annual progress updates
Phase 3: two (5 Dec 2025, 5 Dec 2026). Phase 4: three (5 Dec 2029, 2030, 2031), the third added by reg 28 of SI 2026/701 [6][7].
Duty 6
Report achieved savings in kWh, per measure
Reg 27D: the total, the organisational-purpose breakdown, the measures implemented, each measure's category and each measure's kWh [8][10].
Duty 7
Review the current plan and explain the gaps
Reg 27E: measures not implemented and not expected to be, plus a reason for each — inside the ESOS report and the notification [8].
Duty 8
Declare a plan you were required to produce but did not
Reg 27E(2)(c). Appendix B Table B10 marks this field published by the Scheme Administrator [8][10].
Publication

Table B10, as published

The action plan block of Appendix B, reproduced with its own regulation references. “New” marks a field that did not exist before SI 2026/701 [10].

Notification fieldProvisionNew?Published?
An estimate of energy savings achieved in the compliance period, in kWhReg 27D(1)Yes
Breakdown of those savings by buildings, transport, industrial processes and otherReg 27D(2)(a)No
The measures implemented to achieve the savingsReg 27D(2)(b)NewNo
The energy saving category each implemented measure most closely relates toReg 27D(2)(c)(i)NewNo
An estimate of the savings achieved by each implemented measure, in kWhReg 27D(2)(c)(ii)NewNo
Measures proposed in the current action plan which have not been implementedReg 27E(2)(a)NewNo
For each measure proposed but not implemented, an explanation of the reasonsReg 27E(2)(b)NewNo
Confirmation that the participant was required to produce an action plan but did not do soReg 27E(2)(c)NewYes

Reproduced from Appendix B: Information to provide through the ESOS notification system, Table B10 (Environment Agency, 30 July 2026), which states that where it and the ESOS Regulations 2014 as amended conflict, the regulations take precedence [4][10].

FAQ

ESOS action plan — frequently asked questions

Direct answers on content, deadlines, progress updates, templates, submission, publication and enforcement.

What is an ESOS action plan?

An ESOS action plan is a forward-looking document, signed off by a responsible officer, required under Part 6A of the ESOS Regulations (inserted by the ESOS (Amendment) Regulations 2023). It sets out whether the organisation intends to reduce its energy consumption, the specific energy-saving measures it plans to implement, the estimated savings, and the timescales for delivery. It is submitted to the Environment Agency via the MESOS service after the compliance notification and is followed by annual progress updates. Since SI 2026/701 came into force on 22 July 2026 it is also the document the next phase's notification reviews: regulation 27E requires you to identify measures in your current action plan that were not implemented, and explain why.

When was the ESOS action plan deadline?

The Phase 3 ESOS action plan deadline was 5 December 2024. The Environment Agency then operated an extended window during which late submissions were accepted without remedial action; we have not located a primary Environment Agency publication stating that window's closing date, and it is now closed in any event. That deadline has passed — the live obligations are the annual progress updates (5 December 2025, passed, and 5 December 2026, next due), and a new action plan cycle follows the Phase 4 notification deadline of 5 December 2027, with the Phase 4 action plan itself due 5 December 2028.

When are ESOS action plan progress updates due?

Phase 3 participants must submit two progress updates: the first was due 5 December 2025 and the second is due 5 December 2026. Phase 4 carries three. The Phase 4 action plan is due 5 December 2028 and covers 6 December 2027 to 5 December 2031, with progress updates on 5 December 2029, 5 December 2030 and a third and final update on 5 December 2031 — added by regulation 28 of SI 2026/701. Each update reports implementation progress against the action plan commitments, requires responsible officer sign-off, and is publicly disclosed. Regulation 33A, inserted by regulation 25 of SI 2026/701, deems participants whose energy consumption is zero kWh to have complied with Part 6A, so the progress update duty does not bite on them.

What must an ESOS action plan include?

A compliant action plan states whether the organisation intends to reduce energy consumption, then sets out the energy-saving measures it will take, the estimated energy and cost savings for each, implementation timescales, and how savings will be measured. In practice a robust plan also covers investment requirements and a breakdown across all four organisational purposes (buildings, transport, industrial processes, and any other purpose). It must be signed off by a responsible officer, meaning a director within section 250 of the Companies Act 2006 or a person exercising management control, and be suitable for public disclosure. Since Phase 4, it is worth also tagging each measure with an energy-saving category at plan stage, because regulation 27D(2)(c)(i) requires that category for every implemented measure when you report achieved savings.

How do you submit an ESOS action plan?

Action plans and progress updates are submitted through the Environment Agency's Manage your ESOS reporting (MESOS) online service — the same portal used for compliance notifications. The underlying compliance notification must be filed first; the action plan and progress update forms only become available once it is. Board-level director sign-off is required before submission.

Is there an official ESOS action plan template?

There is no downloadable statutory template for the action plan itself. The MESOS submission form structures the content: intentions, measures, estimated savings and timescales, entered against the categories in the regulations. The Environment Agency's Phase 4 publication page of 30 July 2026 carries six documents, and two of them are templates — but neither is an action plan template. Appendix A3 is an example template of phase 4 ESOS recommendations (the audit output a plan is built from), and Appendix B is a field list of the information to provide through the notification system. The section "What an ESOS action plan must include" on this page walks through each required field, and our ESOS templates page lays the same structure out field by field.

Are there penalties for not submitting an ESOS action plan?

Submission is a legal requirement, but there is no financial penalty for missing it. The Environment Agency's Phase 4 guidance states that regulators will not take enforcement action or issue a penalty relating to the non-submission of an action plan or progress update; the Scheme Administrator publishes the failure instead. Penalties attach to the compliance-date obligations — notification, records, the audit itself and false statements. There is also a specific mechanism worth knowing: regulation 27E(2)(c) requires your Phase 4 notification to carry confirmation that you were required to produce an action plan but did not do so, and Appendix B Table B10 marks that confirmation as published by the Scheme Administrator.

What is the ESOS action plan review under regulation 27E?

The action plan review is a new block inside the ESOS report and the notification of compliance, introduced by regulation 17 of SI 2026/701, which inserts Chapter 3B and regulations 27D and 27E into the ESOS Regulations 2014. Regulation 27E requires you to identify any measures recorded in your current ESOS action plan which have not been implemented and are not expected to be implemented before the end of the compliance period, and to explain the reasons why. For Phase 4 participants that means the plan filed by 5 December 2024 is reviewed inside the notification due 5 December 2027. The review is not a separate submission and, apart from the regulation 27E(2)(c) confirmation, it is not published.

Does the ESOS action plan review get published?

Mostly no. Appendix B of the Phase 4 guidance carries a "Published by the scheme administrator?" column against every notification field. In Table B10 — the action plan and achieved-savings block — the measures not implemented and the explanations for each are marked as notified but not published. Two fields in that block are published: the estimate of total energy savings achieved in kWh, and the confirmation under regulation 27E(2)(c) that a participant required to produce an action plan did not do so. Action plans themselves and progress updates are published; the review around them is not.

What are ESOS achieved savings and how are they reported?

Regulation 27D requires the ESOS report and the notification of compliance to state an estimate of the energy savings the participant achieved during the compliance period — for Phase 4, 6 December 2023 to 5 December 2027 — expressed in kWh. It is reported in four parts: the total estimate, a breakdown by organisational purpose (buildings, transport, industrial processes, other), the measures implemented, and for each measure its energy-saving category and its own kWh saving. Only the combined total is published; the per-measure figures are notified but withheld. Regulation 28 separately changed the progress-update reporting unit from "energy measurement units" to kWh.

What is the difference between an ESOS action plan and an ESOS progress update?

The action plan is the forward-looking commitment, filed once per phase after the compliance notification: what you intend to do, the estimated savings, and when. A progress update is the annual report against that plan: what has actually been implemented, the savings achieved against the savings estimated, the reasons for any variance, revised timescales, and any measures added since. Phase 3 carries two progress updates and Phase 4 carries three. "Progress report" is not a term the regulations use — the statutory instrument is a progress update under regulation 34B.

Who has to sign off an ESOS action plan?

A responsible officer: a director within section 250 of the Companies Act 2006, or a person exercising management control (regulation 30(2)). The Environment Agency's Phase 4 guidance requires director sign-off on the ESOS assessment, the action plan and every progress update before submission through MESOS. Where a participant is a group complying as one, the sign-off sits with a director of the responsible undertaking. Sign-off is a substantive requirement rather than a formality: the notification carries declarations under regulation 31, and a false or misleading statement in a notification is an offence under regulation 47, carrying a penalty of up to £50,000 plus publication.

Terms

The words the regulations use

Term
Action plan
The Part 6A document: intent, measures, estimated savings, timescales. Director-signed and published [1].
Term
Progress update
The annual report against the plan, under reg 34B. The regulations do not use “progress report” [7].
Term
Action plan review
The reg 27E block inside the ESOS report and notification. Not a separate submission, and not published [8].
Term
Energy saving category
The classification each implemented measure is assigned under reg 27D(2)(c)(i) [8].
Term
Organisational purpose
Buildings, transport, industrial processes, other energy uses — the split used for both consumption and achieved savings [10].
Term
Compliance period
Phase 4 runs 6 December 2023 to 5 December 2027. Achieved savings are reported across the whole span [6][10].
Term
Scheme Administrator
The Environment Agency, UK-wide, which collects notifications and publishes what Appendix B marks as published [6].
Term
MESOS
Manage your ESOS reporting — the only submission route for notifications, plans and updates [3].
Authority sources

Sources

Every numbered citation on this page, in order. Legislation and regulator first. All fetched and checked on 8 August 2026.

  1. 1The Energy Savings Opportunity Scheme (Amendment) Regulations 2023 (SI 2023/1182) legislation.gov.uk — inserted Part 6A, the action plan obligation
  2. 2Energy Savings Opportunity Scheme (ESOS): guidance GOV.UK / Environment Agency — the scheme hub
  3. 3Manage your ESOS reporting (MESOS) GOV.UK / Environment Agency — the submission service
  4. 4The Energy Savings Opportunity Scheme Regulations 2014 (SI 2014/1643) legislation.gov.uk — the parent instrument
  5. 5Comply with the Energy Savings Opportunity Scheme (ESOS) phase 4 GOV.UK / Environment Agency, published 30 July 2026 — the publication page and its six documents
  6. 6How to comply with the Energy Savings Opportunity Scheme (ESOS) phase 4 GOV.UK / Environment Agency — milestone table, sign-off, § 15.1 penalties
  7. 7SI 2026/701, regulation 28 legislation.gov.uk — the third progress update, and kWh as the reporting unit
  8. 8SI 2026/701, regulation 17 legislation.gov.uk — inserts Chapter 3B and regulations 27D and 27E
  9. 9The Energy Savings Opportunity Scheme (Amendment) Regulations 2026 (SI 2026/701) legislation.gov.uk — made 23 June 2026, in force 22 July 2026
  10. 10Appendix B: Information to provide through the ESOS notification system GOV.UK / Environment Agency, ODT, 30 July 2026 — twelve tables; Table B10 is the action plan block
  11. 11Appendix A3: Example template of phase 4 ESOS recommendations GOV.UK / Environment Agency, ODT, 30 July 2026 — a recommendations template, not an action plan template
  12. 12Appendices A1 and A2: Report checklists for participants GOV.UK / Environment Agency — ESOS report checklists
  13. 13Appendix C: Advice for complying with ESOS GOV.UK / Environment Agency
  14. 14Appendix D: Useful contacts and information GOV.UK / Environment Agency — regulator contacts by nation

This page is independent reference material about the ESOS Regulations. It is not legal advice, and it is not affiliated with the Environment Agency, DESNZ or any regulator. Where this page and the regulations differ, the regulations govern.

Book a free consultation