ESOS deadlines · the dated register
ESOS deadlines: every date, and the rule behind it
ESOS deadlines follow one rule in regulation 4: four-year compliance periods from 6 December to 5 December, with qualification on the 31 December before the end.
Since Phase 3, each notification is followed by an action plan and progress updates that run into the next phase, so two phases are usually live at once.
Two dates bind in 2026: the Phase 3 progress update on 5 December and Phase 4 qualification on 31 December.
The rule
Two constants generate almost every date
Regulation 4(2) opens each compliance period on the 6th December after the last one ends, and closes it on the 5th December four years later.
The compliance date is the last day of the period, and the qualification date is the 31 December immediately before it, eleven months and five days earlier.
Phase 1 is the only short period: it began when the Regulations came into force on 17 July 2014 and ran to 5 December 2015.
Phase 3’s compliance date is the only one that is neither a 5 December nor a 31 December: it was extended by six months to 5 June 2024.
The extension did not move the Phase 4 clock, which started on 6 December 2023, so for six months organisations were inside Phase 4 while still working to a Phase 3 date.
SI 2026/701 did not amend regulation 4, and the Environment Agency’s Phase 4 guidance restates 5 December 2027 as the Phase 4 compliance date.
| Phase | Qualification | Compliance period | Compliance date |
|---|---|---|---|
| 1 | 31 Dec 2014 | 17 Jul 2014 – 5 Dec 2015 | 5 Dec 2015 |
| 2 | 31 Dec 2018 | 6 Dec 2015 – 5 Dec 2019 | 5 Dec 2019 |
| 3 | 31 Dec 2022 | 6 Dec 2019 – 5 Dec 2023 | 5 Jun 2024 |
| 4 | 31 Dec 2026 | 6 Dec 2023 – 5 Dec 2027 | 5 Dec 2027 |
| 5 | 31 Dec 2030 | 6 Dec 2027 – 5 Dec 2031 | 5 Dec 2031 |
The 2026 dates
Twenty-six days, two phases
5 December 2026 · Phase 3
The further progress update on a Phase 3 action plan, covering 6 December 2025 to 5 December 2026, falls due under regulation 34B(1)(b).
The Phase 3 guidance, updated 30 July 2026, says: “The remaining deadline is to submit the second progress update report by 5 December 2026.”
What it must contain is on ESOS progress report; the phase itself on ESOS Phase 3.
31 December 2026 · Phase 4
Size is tested for Phase 4: at least 250 persons, or turnover in excess of £44 million and a balance sheet total in excess of £38 million.
The figures behind the test are not a one-day snapshot: headcount is a monthly average over the accounting period, and the accounts are those for the year ending on or in the 12 months before the date (Schedule 1 ¶¶5, 10).
Shrinking below the line in 2027 does not take a qualifying group out of Phase 4; the test is on the Phase 4 compliance guide.
Which date binds you
Pick a date, see what falls due next
Which ESOS deadline applies depends on where you stand in two overlapping cycles, so the quickest answer starts from a date.
The finder beside this text places any day from 17 July 2014 to 5 December 2035 in its compliance period and lists the next dated duties after it, each with its provision.
On 30 September 2026 it shows Phase 4, with the Phase 3 further progress update next, then Phase 4 qualification, then the Phase 4 notification.
A group that was not in Phase 3 has no 5 December 2026 duty, and its first ESOS date is the 31 December 2026 qualification test.
A group that was in Phase 3 but will not be large on 31 December 2026 still owes the Phase 3 update, and should tell its regulator it does not qualify for Phase 4.
A group in both carries the Phase 3 plan into its Phase 4 report, which must review it under regulation 27E.
Which ESOS phase is it? · regulation 4
30 September 2026 falls in Phase 4, the compliance period 6 December 2023 to 5 December 2027.
Qualification date 31 December 2026; compliance date 5 December 2027.
- 5 December 2026Phase 3 second progress updatereg 34B(1)(b)
- 31 December 2026Phase 4 qualification datereg 4(3)(b)
- 5 December 2027Phase 4 notification of compliancereg 4(4)(b), reg 29
- 5 December 2028Phase 4 action planreg 34A(7)(b), (10)
Derived from SI 2014/1643 regs 4, 28(2), 34A and 34B and the Environment Agency’s compliance-period table.
Phase 6 is the regulation 4 formula carried forward, not a published date.
Which twelve months
The reference period and the audit data window
The Phase 4 reference period is 12 consecutive months that include 31 December 2026 and, under regulation 22(5)(b), end on or before 5 December 2027.
So the earliest possible window runs from 1 January 2026, and a window ending on 5 December 2027 itself is lawful.
The audit’s own data is limited separately: the GOV.UK ESOS page says it must cover 12 months beginning no earlier than 6 December 2022, and no earlier than 24 months before the audit starts.
Many organisations use a financial year that straddles 31 December 2026, because the meter data and invoices already exist in that shape.
The work that has to fit before 5 December 2027 — the audit, the lead assessor’s review and the sign-off — is on the ESOS energy audit and ESOS lead assessor pages.
Two twelve-month windows · Phase 4
1 · Reference period for total energy consumption (reg 22(5))
- Regulation 22(5)(a): begins no more than 12 months before the qualification date (on or after 31 December 2025).
- Regulation 22(5)(b): ends 31 March 2027, on or before the compliance date, 5 December 2027.
- Environment Agency guidance §4.4 (not the regulation): the period should include 31 December 2026; this one does.
A valid Phase 4 reference period.
2 · Data behind an energy audit (GOV.UK step 5; EA guidance §8.3)
- Begins on or after 6 December 2022.
- Begins within 24 months of the audit start (no earlier than 1 March 2025).
- Ends 31 December 2026, on or before 5 December 2027.
- The audit starts inside the compliance period.
Usable for a Phase 4 audit, provided it was not relied on for an audit in Phase 3.
Rules from SI 2014/1643 reg 22(5), the Environment Agency’s guidance §4.4 on including the qualification date, the GOV.UK ESOS page (rewritten 2 September 2026) and the Environment Agency’s Phase 4 guidance §8.3.
Twelve consecutive months are read as ending the day before the anniversary of the first day.
After notification
Action plan and progress update windows
Every date after a compliance date comes from Part 6A, inserted by SI 2023/1182.
Regulation 34A(10) makes the “relevant compliance period” the one following the period the notification related to, and each window runs from an anniversary of its first day.
For a Phase 4 notification the relevant period is 6 December 2027 to 5 December 2031, so the plan is due by 5 December 2028 and the updates by 5 December 2029, 2030 and 2031.
The third update is new: SI 2026/701 regulation 28 inserted it for compliance periods ending on or after 5 December 2027.
The Environment Agency’s Phase 4 guidance describes the Phase 4 updates as falling “in 2029 and 2030” in its stages list and names three elsewhere; the Regulations say three.
Each date is the last day of a window, so a plan or update may be filed at any point inside it; the ESOS action plan page covers what the plan must say.
Windows from regulations 34A and 34B
Notification related to 6 December 2023 – 5 December 2027.
The relevant compliance period is therefore 6 December 2027 – 5 December 2031.
| Duty | Window, and its last day |
|---|---|
| Action plan reg 34A(7)(b) | 6 December 2027 – 5 December 2028 by 5 December 2028 |
| Initial progress update reg 34B(1)(a) | 6 December 2028 – 5 December 2029 by 5 December 2029 |
| Further progress update reg 34B(1)(b) | 6 December 2029 – 5 December 2030 by 5 December 2030 |
| Final progress update reg 34B(1)(c), inserted by SI 2026/701 reg 28 | 6 December 2030 – 5 December 2031 by 5 December 2031 |
Each date is the last day of a statutory window, not a single filing day.
Both phases
Every action plan and progress update deadline, side by side
| Duty | Phase 3 window | Phase 3 last day | Phase 4 window | Phase 4 last day | Provision |
|---|---|---|---|---|---|
| Action plan | 6 Dec 2023 – 5 Dec 2024 | 5 Dec 2024 | 6 Dec 2027 – 5 Dec 2028 | 5 Dec 2028 | reg 34A(7) |
| Initial progress update | 6 Dec 2024 – 5 Dec 2025 | 5 Dec 2025 | 6 Dec 2028 – 5 Dec 2029 | 5 Dec 2029 | reg 34B(1)(a) |
| Further progress update | 6 Dec 2025 – 5 Dec 2026 | 5 Dec 2026 | 6 Dec 2029 – 5 Dec 2030 | 5 Dec 2030 | reg 34B(1)(b) |
| Final progress update | Not listed by the regulator | — | 6 Dec 2030 – 5 Dec 2031 | 5 Dec 2031 | reg 34B(1)(c) |
The pattern is the same in both phases because both are arithmetic on the first day of the relevant compliance period: 6 December 2023 for a Phase 3 plan, 6 December 2027 for a Phase 4 one.
Each window is twelve months, and the update reports on that window, so filing early does not shorten the period the figure has to cover.
The guidance says an update may be notified at any time during its twelve-month period but encourages filing close to the deadline, so that the savings reported cover as much of the year as possible.
The Environment Agency’s published Phase 3 data shows four in five first updates arriving in the final 30 days, and one in nine after the deadline.
Has the ESOS deadline moved?
Once in law, once in practice, and not for Phase 4
The only compliance date that has moved in law is Phase 3’s, extended by six months from 5 December 2023 to 5 June 2024.
The GOV.UK ESOS page then recorded, on 8 July 2024, that an organisation which had still not notified needed to do so by 6 August 2024, and on 3 October 2024 that the extension had passed.
The Phase 3 action plan has a similar pair of dates: 5 December 2024 in regulation 34A(7)(a), and 5 March 2025 as the date GOV.UK said plans could still be submitted until.
In each pair the first is the legal deadline and the second is how long the Agency said it would accept late filings; they are not interchangeable.
Phase 4 is different: the Environment Agency’s Phase 4 guidance says the scheme regulators cannot amend the 5 December 2027 deadline.
The same passage says the deadline “was revised by the 2026 amendment”, but SI 2026/701 does not amend regulation 4, and 5 December 2027 is the date the 2014 formula has always produced.
If a notification will be late, the guidance’s instruction is to contact your regulator before the date; that does not stop the failure-to-notify offence from running.
Working backwards from 5 December 2027
A quarter-by-quarter sequence for Phase 4
Our indicative order of work, built from the dependencies in the Regulations and the guidance.
No regulator publishes a timetable; only the dates in the last column are fixed.
| When | Work | Why then | Fixed date it serves |
|---|---|---|---|
| Q4 2026 | Map the UK group; test every member; finish the Phase 3 further update | Qualification is tested on 31 December; the Phase 3 update is due on 5 December | 5 Dec 2026 · 31 Dec 2026 |
| Q1 2027 | Fix the reference period; confirm the data exists; choose the route | The period must include 31 December 2026; the route decides whether an assessor is needed | — |
| Q1–Q2 2027 | Appoint the lead assessor; agree site sampling | Site visits need diaries; audit data must start within 24 months of each audit | — |
| Q2–Q3 2027 | Run the audits; estimate savings achieved since 6 December 2023; review the Phase 3 plan | Regs 27D and 27E need the whole Phase 4 period’s story | — |
| Q3 2027 | Write the ESOS report; lead assessor review; seven-day notice by the assessor | The assessor’s outcome starts the reg 21(2A) clock | — |
| Q4 2027 | Responsible officers confirm; notify through MESOS | Sign-off depends on someone else’s diary | 5 Dec 2027 |
| Dec 2027 – 2028 | Draft and notify the Phase 4 action plan | The window opens on 6 December 2027 | 5 Dec 2028 |
Audits do not have to wait: the guidance’s Appendix C lets audit work done at any point in the four years count, so an audit in 2026 or early 2027 is allowed if its data window fits.
The Phase 4 compliance guide sets out each duty in this sequence against its regulation.
What you actually file
Filings, places and publication dates
Every ESOS filing goes through MESOS, the Environment Agency’s online service, which the Regulations call the Notification System.
MESOS opened for Phase 3 registration on 19 March 2024 and for notifications on 30 April 2024, replacing the survey tool used in the first two phases.
The Phase 4 guidance says further information on submitting the Phase 4 notification will be provided, and that there is no charge for submitting it.
Publication runs on its own clock under regulation 10(2), and the guidance gives 10 June 2028 as the Phase 4 publication date.
The notification and the ESOS notification page go into what is asked for; the ESOS reporting page what is published.
| Filing | Where | Published |
|---|---|---|
| Phase 4 notification of compliance | MESOS, by 5 Dec 2027; no charge | 10 Jun 2028, per the guidance |
| Phase 4 action plan | MESOS, by 5 Dec 2028 | Within six months of the deadline |
| Each progress update | MESOS, inside its window | Within six months of the deadline |
| ESOS report | Not filed; kept in the evidence pack | No |
| Evidence pack | Kept to at least 5 Dec 2035 | No |
Phase 3 in full
The Phase 3 dates, statutory and administrative
Phase 3 qualified on 31 December 2022, and its compliance period ran from 6 December 2019 to 5 December 2023.
The notification date was extended to 5 June 2024, and the fourth period began on 6 December 2023 regardless.
The statutory action plan deadline was 5 December 2024, set by regulation 34A(7)(a); the GOV.UK change note of 7 February 2025 said plans could still be submitted until 5 March 2025, which is an acceptance window, not a statutory date.
The plan covers 6 December 2023 to 5 December 2027, which is exactly Phase 4’s compliance period.
The first progress update was due by 5 December 2025, and the second is due by 5 December 2026.
A Phase 3 participant that is large again on 31 December 2026 will review this plan in its Phase 4 report under regulation 27E; see ESOS notification and ESOS reporting.
Regulation 34B(1)(c) applies “for compliance periods ending on or after 5th December 2027”, and the relevant compliance period for a Phase 3 plan ends on exactly that day.
The Environment Agency lists two Phase 3 updates, and no published source settles whether the final-update limb reaches Phase 3 plans.
This register shows no date for it; if it matters to you, ask the Environment Agency.
Missing a date
Which dates carry a penalty
| Date | Duty | Penalty if missed |
|---|---|---|
| Compliance date | Notify compliance | Up to £5,000, plus £500 per working day to 80 working days, plus publication (reg 43) |
| Compliance date | Carry out the ESOS assessment | £50,000, plus £500 per working day to 80 working days, plus publication (reg 45) |
| Any time | Keep the evidence pack | £5,000 plus the cost of confirming compliance, plus publication (reg 44) |
| Action plan date | Notify the action plan | None; the failure is published |
| Progress update dates | Notify each update | None; the failure is published |
The Environment Agency’s approach to setting the amount is in its enforcement and sanctions policy; the ESOS penalties page covers each offence.
If a notification will be late, contact the regulator before the date passes; the regulators are listed on the GOV.UK ESOS page, and the Environment Agency itself is at gov.uk/environment-agency.
The register
Every ESOS date, 2014 to 2035
Dates in the past are marked as passed.
Nothing here is a projection: each date is set by an instrument or published by the regulator.
| Date | What happens | Provision | Status on 30 Sep 2026 |
|---|---|---|---|
| 17 Jul 2014 | Regulations in force; Phase 1 begins | reg 1; reg 4 | Passed |
| 31 Dec 2014 | Phase 1 qualification date | reg 4 | Passed |
| 5 Dec 2015 | Phase 1 compliance date | reg 4 | Passed |
| 31 Dec 2018 | Phase 2 qualification date | reg 4 | Passed |
| 5 Dec 2019 | Phase 2 compliance date | reg 4 | Passed |
| 31 Dec 2022 | Phase 3 qualification date | reg 4 | Passed |
| 29 Nov 2023 | SI 2023/1182 in force: Part 6A action plans | SI 2023/1182 | Passed |
| 6 Dec 2023 | Phase 4 compliance period begins | reg 4(2) | Passed |
| 5 Jun 2024 | Phase 3 compliance date (extended) | EA table | Passed |
| 5 Dec 2024 | Phase 3 action plan | reg 34A(7)(a) | Passed |
| 5 Mar 2025 | Phase 3 plans still accepted until | GOV.UK change note | Passed · not a statutory date |
| 5 Dec 2025 | Phase 3 initial progress update | reg 34B(1)(a) | Passed |
| 22 Jul 2026 | SI 2026/701 in force | SI 2026/701 reg 1 | Passed |
| 5 Dec 2026 | Phase 3 further progress update | reg 34B(1)(b) | Next |
| 31 Dec 2026 | Phase 4 qualification date | reg 4(3)(b) | Upcoming |
| 5 Dec 2027 | Phase 4 notification of compliance | reg 4(4)(b) | Upcoming |
| 5 Dec 2028 | Phase 4 action plan | reg 34A(7)(b) | Upcoming |
| 5 Dec 2029 | Phase 4 initial progress update | reg 34B(1)(a) | Upcoming |
| 5 Dec 2030 | Phase 4 further progress update | reg 34B(1)(b) | Upcoming |
| 31 Dec 2030 | Phase 5 qualification date | reg 4 | Published |
| 5 Dec 2031 | Phase 4 final progress update; Phase 5 compliance date | reg 34B(1)(c); reg 4 | Upcoming |
| 5 Dec 2035 | Phase 4 evidence pack may be discarded after | reg 28(2)(b) | Upcoming |
Which accounts count
Your year end decides which figures are tested
The qualification date is a single day, but the figures tested on it come from a whole financial year.
Schedule 1 uses the accounts for the financial year ending on the qualification date or in the twelve months immediately before it, and the headcount is averaged month by month over that same year.
For a calendar-year company that is the year ending on 31 December 2026 itself, whose accounts will not be finished until well into 2027, so the test may first be run on management figures and confirmed later.
For a company with a March year end it is the year to 31 March 2026, already closed, which is the Environment Agency’s own worked example.
Where an undertaking is close to the line or has recently grown or shrunk, Schedule 1 paragraph 11 requires looking back to the last two consecutive accounting periods at the same size, however far back that is.
The guidance gives two five-year patterns to show the effect: a company large in 2022 and 2023, small in 2024 and 2025 and large again in 2026 is not in scope, while one large in 2022 and 2023, small in 2024, large in 2025 and small in 2026 still is.
| Financial year end | Accounts used for 31 Dec 2026 | Headcount averaged over |
|---|---|---|
| 31 December | Year to 31 December 2026 | January to December 2026 |
| 31 March | Year to 31 March 2026 | April 2025 to March 2026 |
| 30 June | Year to 30 June 2026 | July 2025 to June 2026 |
| 30 September | Year to 30 September 2026 | October 2025 to September 2026 |
Dates inside Phase 4
The clocks that run before 5 December 2027
| Event | What it starts or decides | Source |
|---|---|---|
| 31 December 2026 | Who is in Phase 4; a later change in size does not affect eligibility | reg 4(3)(b); EA guidance §3.2 |
| 31 Dec 2026 – 5 Dec 2027 | An undertaking in insolvency proceedings at any point in this window is excluded | reg 16, as amended by SI 2026/701 reg 6 |
| 31 Dec 2026 – 5 Dec 2027 | An undertaking that leaves a qualifying group still complies: with its old group, its new one, or alone | EA guidance §2.8 |
| 31 Dec 2026 – 5 Dec 2027 | An undertaking bought from a non-qualifying seller need not be counted | EA guidance §2.8 |
| On 31 December 2026 | Assets held then count; those given up before 5 December 2027 may be left out | EA guidance §4.3.1 |
| Lead assessor’s review outcome | Starts seven days for the assessor to notify their approval body | reg 21(2A) |
| 6 December 2023 onwards | ISO 50001 certificates issued from this date can support Phase 4; they must still be valid on 5 December 2027 | reg 33; EA guidance |
| 6 Dec 2023 – 5 Dec 2027 | The period whose energy savings the report must estimate | reg 27D; EA guidance §10.4 |
Most ESOS planning focuses on the two headline dates, but several smaller clocks run between them and decide what the assessment has to cover.
The qualification date fixes the population: the guidance says a change in status after it does not affect eligibility for the period.
Group changes after it are handled by a rule of their own, so an acquisition or disposal in 2027 changes who notifies for whom, not whether the undertakings comply.
The savings-achieved estimate looks back across the whole period from 6 December 2023, which is why a Phase 4 report needs records of what was implemented in 2024 and 2025, not just 2027.
If a date is missed
What happens, and how a penalty accrues
Missing the compliance date can trigger two offences: failing to notify under regulation 43, and failing to carry out an assessment under regulation 45.
The daily limb does not run from the compliance date itself: the guidance says it runs from the day after the relevant notice is served until the breach is remedied, capped at 80 working days.
That gives statutory ceilings of £45,000 for failing to notify and £90,000 for failing to carry out an assessment, each with publication of the undertaking’s name, the requirement breached and the amount.
The regulators work through three notices: a compliance notice asking for information, an enforcement notice saying what must be done, and a penalty notice imposing the penalty.
For a new entrant in its first compliance period, the Environment Agency’s Annex 2 says it will normally cap the initial penalty for failing to audit at £5,000.
Missing an action plan or progress update date carries no penalty; Part 8 does not name those duties, and the failure is published instead.
Any determination or notice can be appealed on an error of fact, an error of law or unreasonableness, to the First-tier Tribunal for England, Wales and offshore, the Scottish Ministers, or the Planning Appeals Commission in Northern Ireland.
The calculator beside this text shows how the fixed and daily limbs combine for each offence.
Part 8 of SI 2014/1643 · statutory maxima
Maximum so far: £5,000
Fixed £5,000 + 0 working days × £500 = £0 · statutory ceiling £45,000
The notification of compliance under regulation 29 was not made by the compliance date.
Every Part 8 penalty also carries publication: the regulator names the undertaking, the requirement breached and the amount.
An indicative reading of SI 2014/1643 regs 41 and 43–47, and the Environment Agency’s enforcement policy Annex 2.
The regulator sets the actual amount; nothing here is advice.
The dates that have passed
Phases 1 to 3, from the record
The first three phases are closed, but their dates still matter because data, plans and evidence packs carry forward.
Phase 1 ran from 17 July 2014, when the Regulations came into force, to 5 December 2015, and its qualification thresholds were set in euros and converted on the qualification date.
Before the first deadline the GOV.UK page told organisations that could not notify by 5 December 2015 to say so by that date using an online form.
Phase 2 qualified on 31 December 2018 and closed on 5 December 2019, still under the euro thresholds of €50 million turnover and €43 million balance sheet.
Phase 3 qualified on 31 December 2022, the first qualification date under the sterling thresholds of £44 million and £38 million, which apply from 31 December 2020.
It was also the first phase with action plans and progress updates, inserted by SI 2023/1182 a week before the period ended, and the first filed through MESOS.
| Date | What the record shows |
|---|---|
| 17 Jul 2014 | Regulations in force; Phase 1 begins |
| 31 Dec 2014 | Phase 1 qualification date; euro thresholds converted at that day’s rate |
| 3 Nov 2015 | Organisations told to inform the EA by 5 December 2015 if they could not notify |
| 5 Dec 2015 | Phase 1 compliance date |
| 31 Dec 2018 | Phase 2 qualification date |
| 5 Dec 2019 | Phase 2 compliance date |
| 31 Dec 2022 | Phase 3 qualification date, the first in sterling |
| 29 Nov 2023 | SI 2023/1182 in force |
| 19 Mar 2024 | MESOS opens for Phase 3 registration |
| 30 Apr 2024 | MESOS opens for notifications |
| 5 Jun 2024 | Phase 3 compliance date, as extended |
| 6 Aug 2024 | Late Phase 3 notifications asked for by this date |
| 5 Dec 2024 | Phase 3 action plan |
| 5 Mar 2025 | Phase 3 action plans still accepted until |
| 5 Dec 2025 | Phase 3 initial progress update |
The next phase
Phase 5, already dated
Phase 5 needs no new legislation to exist: regulation 4 produces a compliance period from 6 December 2027 to 5 December 2031, a qualification date of 31 December 2030 and a compliance date of 5 December 2031.
The Environment Agency’s Phase 4 guidance lists those dates in its compliance-period table and says status on 31 December 2030 will decide who is in.
Phase 5’s compliance period is the same four years as a Phase 4 action plan’s relevant period, so the final Phase 4 progress update and the Phase 5 notification share a last day.
What Phase 5 will ask is not settled: DESNZ has said it intends to consult on SECR and ESOS later in 2026, and the ESOS Phase 5 page follows it.
Date vocabulary
The terms the dates are written in
| Term | Meaning | Provision |
|---|---|---|
| Compliance period | The four years from 6 December to 5 December in which an assessment is done | reg 4(2) |
| Qualification date | The 31 December immediately before the compliance date; size is tested on it | reg 4(3) |
| Compliance date | The last day of the compliance period, by which the notification is made | reg 4(4) |
| Reference period | Twelve months including the qualification date and ending on or before the compliance date | reg 22(5) |
| Relevant compliance period | For an action plan, the period after the one the notification related to | reg 34A(10) |
| Relevant event | For an update, the plan’s notification or the previous update’s | reg 34B(8) |
| Relevant reporting period | The twelve-month window an update reports on and is filed in | reg 34B(8) |
| Notification of compliance | The filing that confirms the assessment was done | reg 29 |
Alongside other regimes
ESOS dates beside the rest of the calendar
ESOS runs on its own four-year clock, separate from annual reporting: SECR sits in the directors’ report each year, and ISO 50001 certificates run on their own cycles, with ISO publishing the standard.
A certificate relied on for Phase 4 must be issued on or after 6 December 2023 and valid on 5 December 2027; see ISO 50001 and ESOS.
For listed companies, the dated register for UK SRS sets out the sustainability reporting dates, and the standards editorial at sustainabilityreportingstandards.co.uk keeps its own timeline; ESOS and UK SRS covers where one dataset serves both.
The 2025 post-implementation review of the Regulations is DESNZ’s account of how the scheme has worked, and the ESOS compliance guidance page compares the official documents.
The full duty set is on ESOS requirements, the instruments on ESOS legislation, and the scheme on the Energy Savings Opportunity Scheme.
This site is an independent reference; see the privacy policy and terms of service.
Frequently asked
ESOS dates, answered
What is the next ESOS deadline?
For Phase 3 participants, 5 December 2026, the last day for the second progress update on the Phase 3 action plan, covering 6 December 2025 to 5 December 2026.
For everyone, the Phase 4 qualification date is 31 December 2026, and the Phase 4 notification of compliance is due by 5 December 2027.
What was the ESOS Phase 3 deadline?
The Phase 3 compliance date was extended by six months to 5 June 2024.
The Phase 3 action plan was due by 5 December 2024 under regulation 34A(7)(a), and the Environment Agency accepted plans until 5 March 2025.
The progress updates are due by 5 December 2025 and 5 December 2026.
What was the ESOS Phase 3 qualification date?
31 December 2022.
The Phase 3 compliance period ran from 6 December 2019 to 5 December 2023.
What are the ESOS Phase 4 dates?
The compliance period runs from 6 December 2023 to 5 December 2027.
The qualification date is 31 December 2026 and the notification of compliance is due by 5 December 2027.
The action plan is due by 5 December 2028 and three progress updates by 5 December 2029, 5 December 2030 and 5 December 2031.
Has the ESOS deadline moved?
Only once.
The Phase 3 compliance date was extended by six months to 5 June 2024.
The Phase 4 compliance date of 5 December 2027 has not moved: SI 2026/701, in force 22 July 2026, changed the compliance routes and added duties but did not amend regulation 4.
Which twelve months does the ESOS Phase 4 data cover?
The reference period is 12 consecutive months that include 31 December 2026 and end on or before 5 December 2027, under regulation 22(5). So it can start no earlier than 1 January 2026.
The audit data itself must cover 12 months beginning no earlier than 6 December 2022 and no earlier than 24 months before the audit starts.
When is the ESOS action plan deadline?
For Phase 4, 5 December 2028: the plan may be notified at any time from 6 December 2027 to that date, under regulation 34A(7)(b) and (10).
For Phase 3 the statutory deadline was 5 December 2024.
Is there a penalty for missing an ESOS progress update?
No. Part 8 of the Regulations attaches no penalty to the action plan or progress update duties, and the Environment Agency’s guidance says regulators will not take enforcement action for their non-submission.
The failure is published.
Missing the notification of compliance is penalised: £5,000 plus £500 per working day, capped at 80 working days.
When did ESOS Phase 4 start?
On 6 December 2023, the day after the Phase 3 compliance period ended.
Phase 4 runs to 5 December 2027.
Because Phase 3’s notification date was extended to 5 June 2024, Phase 4 had already started while Phase 3 notifications were still being filed.
When is ESOS Phase 4 due?
The Phase 4 notification of compliance is due by 5 December 2027.
The Environment Agency’s guidance says the regulators cannot amend that deadline, and there is no charge for submitting the notification.
What year is ESOS Phase 3?
Phase 3 covered 6 December 2019 to 5 December 2023, with a qualification date of 31 December 2022 and an extended notification date of 5 June 2024.
Its action plan and progress updates run from 2024 to 2026, the last due by 5 December 2026.
Was the ESOS Phase 3 deadline extended to August 2024?
Not in law.
The compliance date was extended to 5 June 2024.
GOV.UK’s update log then recorded on 8 July 2024 that an organisation that had not yet notified needed to do so by 6 August 2024, and on 3 October 2024 that the extension had passed.
When will the Phase 4 ESOS data be published?
The Environment Agency’s Phase 4 guidance gives 10 June 2028 as the publication date for the fourth compliance period.
Regulation 10(2) requires publication within six months of the compliance date or of a later filing.
When is ESOS Phase 5?
Phase 5 runs from 6 December 2027 to 5 December 2031, with its qualification date on 31 December 2030 and its compliance date on 5 December 2031, the same day the final Phase 4 progress update is due.
How long must ESOS records be kept?
Regulation 28(2)(b) requires the evidence pack for a compliance period to be kept for at least two further compliance periods, so the Phase 4 evidence pack must be kept until at least 5 December 2035.
Sources
Primary sources
Every figure, date and status on this page traces to the instrument’s owner.
Secondary commentary is never the source for a number.
- legislation.gov.ukSI 2014/1643, regulation 4 — compliance periods and dates
The rule behind every qualification and compliance date.
- legislation.gov.ukSI 2014/1643, regulation 22 — the reference period
Twelve months that include the qualification date and end on or before the compliance date.
- legislation.gov.ukSI 2014/1643, Part 6A — action plans and progress updates
The windows behind the 2024–2031 dates: regs 34A(7), 34A(10), 34B(1), 34B(8).
- legislation.gov.ukSI 2026/701, regulation 28 — the final progress update
Inserts reg 34B(1)(c) for compliance periods ending on or after 5 December 2027.
- legislation.gov.ukThe Energy Savings Opportunity Scheme (Amendment) Regulations 2026 (SI 2026/701)
In force 22 July 2026; it does not amend regulation 4.
- legislation.gov.ukThe Energy Savings Opportunity Scheme (Amendment) Regulations 2023 (SI 2023/1182)
Inserted Part 6A, which is why Phase 3 is the first phase whose duties outlast its compliance date.
- legislation.gov.ukSI 2014/1643, regulation 10 — publication
The six-month publication clock.
- legislation.gov.ukSI 2014/1643, regulation 28 — the evidence pack
Kept for at least two further compliance periods.
- Environment AgencyHow to comply with the Energy Savings Opportunity Scheme (ESOS) phase 4
The five-period table, including the Phase 3 extension and the Phase 5 dates.
- Environment AgencyComply with the Energy Savings Opportunity Scheme (ESOS): phase 3
Updated 30 July 2026: the remaining Phase 3 deadline is the second progress update, 5 December 2026.
- GOV.UK (Environment Agency)Energy savings opportunity scheme (ESOS): find out if you qualify and how to comply
The Phase 3 action plan acceptance window and the audit data window.
- legislation.gov.ukSI 2014/1643, Part 8 — civil penalties
Which dates carry a penalty and which do not.